VDA 4985 DELJIT vs VDA 4984 DELFOR: How JIT Call-Off Sequencing Actually Differs
If you supply sequenced parts into a German OEM plant, two VDA demand messages shape your week. VDA 4984 (DELFOR) is the delivery forecast: quantities per part and date, from tomorrow into next quarter. VDA 4985 (DELJIT) is the JIT call-off: a pull signal that tells you which parts to build, in which order, for a delivery window measured in hours. Both come from your customer and both carry quantities and dates; either one gets blamed when something stops at the line.
This guide covers what each message is for, how they fit together, and where the reconciliation traps sit. New to DELFOR? Start with our DELFOR introduction.
Two roles: planning signal versus sequence pull
| VDA 4984 (DELFOR) | VDA 4985 (DELJIT) | |
|---|---|---|
| Direction | Customer to supplier | Customer to supplier |
| Horizon | Days to months (firm plus forecast zone) | Hours, tied to live production |
| Granularity | Quantities per part per date | Positions per part per sequence number |
| Binding level | Firm in the short zone, planning signal beyond it | Firm: build and ship exactly this, in this order |
| Typical parts | All materials, incl. bulk and VMI | Sequenced modules: seats, cockpits, bumpers, battery trays |
| Miss a message and | plan drifts, complaints follow | the line stops, escalation in minutes |
A DELFOR answers "how many parts will this plant need, and when?" A DELJIT answers a sharper question: which specific positions, in which exact order, must reach which dock at which minute? Sequenced module lines consume parts in an order tied to individual vehicle bodies, and the supplier builds to sequence against a receiving window with little buffer. A forecast cannot express that; the gap is what DELJIT closes.
The typical timeline across both messages
The DELFOR lays out demand for the coming weeks, firm in the near zone and forecast beyond; planning converts it into capacity and material orders. Close to the build date, the DELJIT tightens the pull to hours, listing the positions the line consumes, each tied to a sequence number identifying a vehicle order. Two identical parts with different sequence numbers are different deliveries; they may carry different colours or trim codes.
When the truck leaves, you report the shipment back with a VDA 4987 DESADV: plan, pull, proof. Our DESADV article covers the reporting side, and the ORDERS versus DESADV field comparison shows which values the despatch advice must echo back.
What is inside each message
The DELFOR side is well defined: the envelope opens with UNB and UNH, where the message identifier names DELFOR with the release your guideline specifies. The header carries a BGM document code (the profile code list runs 241 for forecast with firm zone, 236 forecast only, 242 JIT), the message date in DTM+137, the scheduling agreement reference in RFF, and the party network in NAD: buyer, seller and ship-to. Item lines start at LIN with the customer part number, with PIA for your own and IMD for the description. The schedule itself combines SCC (SCC+4 marks firm quantities, SCC+1 forecast ones), QTY (VDA 4984 leans on cumulative figures, so read the qualifier) and DTM with the delivery date or window. The full walkthrough is our field-by-field DELFOR guide.
A DELJIT keeps the same EDIFACT envelope discipline, but its content is built around sequence: a call-off header (BGM, message date, reference back to the scheduling agreement, the same NAD parties), a location section for the assembly line, station or unloading point, item identification as in the DELFOR, and sequence detail with the required quantity, the production date and time window, and a RFF sequence reference tying each position to a specific vehicle order. Exact layouts, code lists and qualifiers vary between OEM guidelines; field-level details are governed by the latest guideline issued by your trading partner. Treat any generic DELJIT description as orientation rather than specification.
The three reconciliation traps engineers hit most
1. Mixing quantity bases
Your DELFOR often speaks in cumulative figures: a running total ordered or received up to a date, not the amount due on that date. The DELJIT speaks in discrete positions. Comparing the two without converting first manufactures phantom shortages. Convert both sides to discrete quantities per part per date before comparing, and keep the agreement reference from RFF as the join key.
2. Time zones and date formats
Every date rides in a coded format, commonly 102 (CCYYMMDD) or 203 (CCYYMMDDHHMM), and a JIT window is only as good as the timezone it was written in. A production time read in your ERP's timezone instead of the plant's shifts the window by an hour or more, which is the tolerance JIT does not have. Check the format code on every DTM segment, confirm the plant's timezone, and flag any two-digit year: in a syntax version 4 interchange that is a migration leftover, not a valid date.
3. Duplicate and superseded sequence numbers
Call-off messages supersede each other quickly, and your process must consume the newest file completely before the next one arrives. The failure mode is subtle: a sequence number that already appeared comes back with different content, and a system that processes files out of order ships against stale positions. Treat sequence numbers as unique per call-off version and escalate when one reappears with changed quantities.
Frequently asked questions
Is VDA 4985 the same as VDA 4988?
Both describe DELJIT-based JIT call-offs: sequenced, hours-horizon demand. In the VDA recommendation family, 4985 is the DELJIT message itself; OEMs publish their own DELJIT-based profiles on top of it. The VDA 4988 article walks through one such profile. Your layout details follow your partner's guideline.
Which message is binding for my shipment?
Inside its horizon, the DELJIT is firm: build and ship exactly the positions it lists, in order. Where no DELJIT exists for a part or date, the firm zone of the DELFOR applies.
Do I still need the DELFOR if I get DELJIT?
Yes. Capacity planning, material availability and staffing ride on the DELFOR weeks ahead; the DELJIT covers the last hours. Dropping the DELFOR blinds your planning; ignoring the DELJIT blinds your shipping.
What happens if I ship against an outdated DELJIT?
Positions, quantities or sequence numbers may have changed, and the line consumes boxes in call-off order. The shipment risks refusal at the dock even when part numbers look right. Consume each new file completely before processing anything.
Where can I validate before go-live?
Run the structural check before the data reaches your ERP. The VDA 4984 validator checks envelope integrity, mandatory segments, code lists, date formats and control counts locally in your browser; the VDA 4987 validator does the same for the despatch advices you send back.